Phend & Brown Announces Details Of Paving and Bridge Replacement Projects

Phend & Brown Inc. announced details of a paving and bridge replacement project for U.S. 30 from 0.15 miles west of Ind. 19 to 3.19 miles east of Ind. 15.

Changing weather conditions and/or internal schedule changes may alter the dates. Traffic control signage will be provided in advance of and during any closure, according to a news release from Phend & Brown.

Asphalt paving between Fox Farm Road and Center Street in Warsaw started Monday and will go through the end of June. It will include asphalt patching. Milling and asphalt placement will be performed between 7 p.m. to 6 a.m. Single-lane closures will be set up where work will be performed every day. Expect significant delays during this operation.

Bridge replacement will take place between CR 300N and Fox Farm Road, and is scheduled to start April 4 through the middle of July. Maintenance of traffic will be set up starting Monday, April 4. Eastbound lanes will be closed starting April 11 between CR 300 and Fox Farm Road. All traffic will be switched to the westbound lanes, with one lane of traffic in each direction. Expect significant delays during this operation.

Motorists are advised to seek alternate routes due to anticipated traffic delays, according to the release.